
Technical Bulletin # P-02
Why You Cannot Use Schedule 40
Threaded Pipe In Condenser Water Applications

THE PROBLEM:
Over the life-span of any building
property, the replacement, renovation or addition of building services piping
is a frequent occurrence. Due to the fact that operating pressures of even the
tallest buildings rarely exceeding 250 PSI, pressure is rarely a factor in the
selection of pipe schedule.
Installations of small diameter threaded
black pipe generally use Schedule 40 automatically - with little thought given
to the physical wall thickness limitations of the pipe itself. As a result, it
is not uncommon to find premature failure of relatively new installations, as
well as examples of properties which have replaced such small diameter piping
on a regular basis of every four, five, or six years. Yet in contrast, other
properties, decades old, often show long service life at their smaller diameter
piping.
Allegations of poor or unsatisfactory
chemical water treatment is almost always cited in such failures, although in
most cases, testing indicates an acceptable to moderate corrosion rate. In
fact, more than 50% of the original pipe wall is often removed in the threading
process, leaving little material remaining. Joint compounds and sealants, or
the degree to which the connection is tightened, is rarely capable of holding
back water once the threaded wall area is penetrated by corrosion.

The below Table 4A well illustrates the
degreee to which the threading process weakens Schedule 40 pipe. At the
smallest sizes, the amount of wall lost during threading actually equals
approximately 65% of the original pipe wall. Such initial high wall loss,
coupled with a corrosion rate anywhere exceeding 2.0 MPY, will inevitably
produce a premature pipe leak.
Table 4A - Wall Loss After Threading

THE SOLUTION:
The long established standard piping
formula, known as the Barlow formula, (Piping Handbook, Nayar, 6th Edition,
C.138) is used to calculate the pressure that a section of pipe of known
thickness will tolerate, and is represented as:
tm = PD/2SE + A
This formula takes into account variances
in:
- Pipe Diameter
- Internal Pressure
- Material Stress Factor
- Temperature
- Corrosion Allowance
- Mill Tolerance
- Material Strength
- Joint Preparation And
Efficiency
The minimum pipe wall thickness derived
by this calculation is relevant for all types of pipe, and for all materials,
and is the standard by which design engineers specify the materials for new
building piping construction.
In general, Schedule 40 steel piping
satisfies the engineering requirements of most building applications. However,
under certain conditions and pipe sizes, special consideration must be taken to
ensure that threading or grooving does not reduce the pipe wall thickness past
the permissible minimum dimensions.
For illustration, ECI has prepared Table
4B showing a series of calculations for carbon steel black pipe in sizes 3/4
in. through 3 in. Different configurations of Schedule 40 vs. Schedule 80, Open
vs. Closed, and Welded vs. Threaded, are presented.
View Table
P-02B.
By reviewing the two far right columns
comparing both new original pipe wall thickness and calculated minimum
acceptable wall dimensions, you can easily understand the threat of using
Schedule 40 pipe under certain operating conditions. While corrosion activity
is still the major factor in piping failures, in fact, new Schedule 40 pipe
does not meet minimum minimum thickness requirements in threaded open water
applications, and should not be used.
As can be seen in our table, the primary
cause of failure to meet minimum specifications is the amount of pipe wall
removed in the threading process. Secondary to that is the higher corrosion
rate factor specified for open water condenser systems - a 65 mil lifetime
corrosion allowance we have well documented as being far too low for current
operating conditions.
ECI has long used the Barlow formula in
all ultrasonic piping evaluations, and has found the resulting minimum
acceptable wall thickness and remaining life prediction estimates accurate and
reliable. It is the firm recommendation of ECI that Schedule 80 black iron pipe
should be used exclusively under such conditions - regardless of operating
pressures.
The below photograph illustrates the
typical evolution of a threaded joint failure, and shows that under the same
corrosion characteristics, threaded joints will always fail prematurely. In
this investigation, failure of the pipe threads began within 4 years of
installation. With 2 in. Schedule 40 pipe at 0.154 in. original wall, less
0.087 in. during the threading process, and having an identified a 7.2 MPY
corrosion rate over a period of 3.5 years, wall thickness at the threaded areas
was just under 0.042 in. or 42 mils at the time of testing.

The use of Schedule 40 threaded pipe at
fixtures such as temperature wells, pigtails, pressure gauges, and control
sensors also presents the same threat. If located before a shut-off valve, the
failure of such a piping component can require the shut down of the entire
piping system for repair. Shown below, leakage at the temperature well has
developed past an encrustation or iron oxide at the threads, to an actual
dripping leak.
Even under controlled corrosion
conditions, threaded Schedule 40 pipe does not offer long service life, as
shown below by this evaluation of an 11 year old condenser water system. Here,
a controlled 2-3 MPY corrosion rate still created multiple failures within a
short period of time. The brass valve to carbon steel connection, a common
installation scenario without benefit of a galvanic coupling or insulator,
simply accelerated the corrosion process.

Under extremely high corrosion
conditions, the installation of threaded Schedule 40 pipe can present
widespread operating problems. In the below example, a high corrosion rate of
near 20 MPY produced leaks at many threaded fittings within 2-1/2 years of
start-up. It should be noted that while Schedule 80 pipe would provide more
wall thickness and therefore greater pipe life in the below example, it would
not offer substantially greater service life under such high corrosion
conditions.

We therefore strongly recommend using
Schedule 80 or Extra Strong pipe in all threaded applications serving condenser
water or steam condensate locations, or where a high corrosion rate is
anticipated. Establishing a strong building specification for such construction
materials is also advised.



